Date: Wed, 06 Jul 2005 12:40:07 -0700 To: heafield From: Joe Monaly Jr Subject: letter 2 At 04:03 PM 6/29/2005 -0700, Nunez, William wrote: > Joe, > >Do we have a schedule as to when the east and west units will have data. > >Bill Hi Bill, In addition to the previous items, you should also note: + The AC in the MDF trailer may or may not be working, I was unable to get it to function this morning. + We need at least one NEMA 6-20L installed in the MDF for the switch. The electrical schedule provided was not followed. + The network drop for the security panels do not appear to be installed. + Additional drops for the computer labs are not pulled (in one case this makes sense since there is no where to pull the drops to). + None of the fiber is terminated (simply put, even if we could turn on our electronics, there is no way to connect the electronics from one location to another). I assume that the floor openings will be sealed and the conduits fire-stopped when the cabling work is completed. joe. ----- Joe Monaly Jr. California Institute of Technology Network Engineer Tech Dev and Deployment/NOC, I.T.S. jemonaly MS 214-81 626.395.2109